• Identification and subsequent, safe removal (specialist) of switch gear with ACMs

• Strip out of all redundant electrics and boards Incl. pyro,

• Hire (generator) and connections thereof to supply temporary power during shut down periods (for our testing and also whilst demolition works took place etc.),

• Complete and full re wire throughout,

• New PIR lighting installed throughout, time switches to other rooms where required,

• Installation of new fire alarm system wit call points, detectors and heat sensors,

• Installation of new intruder alarm,

• Emergency lighting installed and designed,

• Floor boxes throughout,

• External security lighting and photocells,

• New Switch Room formed and completely new load centre with tray work/containment throughout office.

• Upgrade Earthing and separate from the Hazard TT arrangement

• 3 compartment DADO trunking assisting IT to pull through and connect CAT5

• New 600x600 recessed Modular fittings,

• Replacement of 3 x faulty flood lights,

• New Batten strips where designated,

• Door Entry system with key fob access including intercom,

• New T5 strips where designated,

• DDA Compliant; Disabled Toilet alarm kit,

• New bulkheads, 

• Extractor unit installation (in WCs),

• Handryers,

• Design, commissioning and certifying new Fire Extinguishers throughout,

• Supply and undertake a PAT test and certify (Kettles, Toasters, Microwaves),

• Full Electrical Installation Certification, Commissioning and handover.

preston

Full office redevelopment, by Consilium.

All the office wiring was in critical condition.